What is 'run-of-river' hydropower, a dominant technology type in Nepal's generation mix?
Correct answer: A plant that generates electricity mainly from the natural flow of a river with minimal storage
Run-of-river plants use the river's natural flow with little to no storage capacity, making their output highly dependent on seasonal water flow.
-
What is a 'power purchase agreement' (PPA) in the context of NEA's dealings with independent power producers?
Correct answer: A contract fixing the price and terms under which NEA buys electricity from a generator
A PPA is a long-term contract specifying the price, duration, and terms under which NEA purchases electricity from a power producer.
-
What does 'transmission and distribution (T&D) loss' refer to in an electricity utility's operations?
Correct answer: Electrical energy lost while moving from generation to end users, through technical and non-technical causes
T&D losses include technical losses (such as resistance in lines) and non-technical losses (such as theft), reducing the electricity actually billed to consumers.
-
Why does Nepal's hydropower generation typically peak during the monsoon season and decline in the dry winter months?
Correct answer: River flow, fed heavily by monsoon rain and snowmelt, is much higher in the monsoon than in dry winter months
Most of Nepal's rivers are fed by monsoon rains and snowmelt, so flow and hydropower output are much higher in wet months than in dry winter months.
-
What is an 'independent power producer' (IPP) in Nepal's electricity sector?
Correct answer: A private or non-NEA entity that generates electricity, typically selling it to NEA under a PPA
IPPs are private or non-NEA entities licensed to generate electricity, typically selling their output to NEA through power purchase agreements.
-
Why is reliable grid connectivity essential for newly built hydropower projects in Nepal?
Correct answer: Without a transmission connection, generated electricity cannot reach consumers or be sold
A hydropower plant's generated electricity must be evacuated through transmission and distribution infrastructure to reach the market, making grid connectivity critical to project viability.
-
What is 'load forecasting' used for by a utility such as NEA?
Correct answer: Predicting future electricity demand to plan generation and infrastructure needs
Load forecasting estimates future electricity demand, helping utilities plan generation capacity, transmission investment, and import/export needs.
-
What is a 'dry season energy deficit' in Nepal's power sector?
Correct answer: A shortfall in domestically generated hydropower during winter months, often met through imports
Because river flows drop in the dry season, domestic hydropower generation falls short of demand, a gap historically bridged through electricity imports.
-
What does 'captive power' mean in an industrial context relevant to electricity utilities?
Correct answer: Power generation facilities owned and operated by a consumer primarily for its own use
Captive power refers to generation facilities built by industries or large consumers mainly to meet their own electricity needs, sometimes independent of the grid utility.
-
Why is diversifying Nepal's energy mix beyond hydropower (e.g., with solar) considered valuable from a planning perspective?
Correct answer: It can help offset hydropower's seasonal dry-season shortfall and reduce reliance on a single source
Solar and other sources can complement hydropower's seasonal variability, particularly helping during the dry season when river flows and hydropower output are lower.