Nepal Electricity Authority (NEA) MCQ Questions with Answers – Practice Set 2

Nepal Electricity Authority (NEA) MCQ Questions with Answers – Practice Set 2

10 questions · 15 minute time limit

Read Exam Guide

You can take this quiz as a guest. Log in first if you want it saved to your progress history.

Answer Key & Explanations

  1. NEA stands for:

    Correct answer: Nepal Electricity Authority

    NEA is the Nepal Electricity Authority, the state-owned utility for electricity generation, transmission, and distribution.

  2. NEA's core responsibilities include:

    Correct answer: Generation, transmission, and distribution of electricity in Nepal

    NEA is vertically integrated, covering generation, transmission, and distribution of electricity across most of Nepal.

  3. Most of Nepal's installed hydropower capacity is of which general type, due to the country's steep rivers and seasonal flow variation?

    Correct answer: Run-of-river

    Nepal's hydropower is mostly run-of-river, generating power from river flow without large storage reservoirs, which causes seasonal output variation.

  4. Nepal historically experienced severe scheduled power cuts that were largely eliminated around the mid-to-late 2010s due to improved supply management. What is this practice of rationing electricity during shortage called?

    Correct answer: Load shedding

    Load shedding is the deliberate, scheduled cutting of electricity supply to manage demand during shortages, a situation Nepal suffered for years before supply improved.

  5. Nepal's hydropower generation tends to be highest during which season, creating a seasonal surplus/deficit pattern?

    Correct answer: Monsoon (wet season), with lower output in the dry winter months

    River flow, and hence hydropower generation, peaks during the monsoon and drops significantly in the dry winter season.

  6. Nepal engages in cross-border electricity trade primarily with which neighboring country?

    Correct answer: India

    Nepal's power grid is interconnected with India, enabling import during shortages and export of surplus power.

  7. A transmission line, as distinct from a distribution line, in an electricity grid generally:

    Correct answer: Carries electricity at high voltage over long distances between generation sites and substations

    Transmission lines move bulk electricity at high voltage over long distances; distribution lines then carry lower-voltage power to end users.

  8. Distribution loss in an electricity utility refers to:

    Correct answer: Electricity lost between generation/supply points and billed consumption, due to technical and non-technical factors

    Distribution (or transmission and distribution) loss measures the gap between electricity supplied and electricity actually billed, from technical losses and theft or leakage.

  9. Upper Tamakoshi, one of Nepal's notable hydropower projects, is an example of which project type?

    Correct answer: A domestically significant run-of-river hydropower project

    Upper Tamakoshi is a major run-of-river hydropower project developed to help meet Nepal's domestic electricity demand.

  10. Electrical energy consumption is typically measured and billed to consumers in which unit?

    Correct answer: Kilowatt-hour (kWh)

    Electrical energy use is measured in kilowatt-hours (kWh), the standard billing unit for electricity consumption.